Development phases

The project "A Step Towards Accessible Belgrade" consists of five phases that will be implemented within the five-year cycle, ending in December 2021. Below, you can see a detailed development plan that began in 2017 ......
Phase 1
(End - 20/02/2018)
- System development (dostupnibeograd.rs)
- Development of BGDzaSVE android app
- Development of BGD4ALL android app
- System testing and debugging
- Creating an initial list of 400 accessible locations
- Inserting the initial list of 100 accessible locations in the system
- Initial system improvement in cooperation with experts
- Testing the upgraded version of the system
- Inserting additional list of 300 accessible locations in the system
- Translating into English
- Translated content inserting
- Other content inserting
- Releasing the system into production
- System promotion at the 40th International Tourism Fair
- Official promotion of the system with the Telenor Foundation and partners Phase 2
(End - 31/12/2018)
- Creating a new list of additional 700 accessible locations and public areas (a certain number of locations will be provided by Althea and Tourism Organization of Belgrade))
- Creating a list of the city traffic infrastructure (dropped curbs, tactile guide lines, sound traffic lights, accessibility of
underground passages) and terrain constitution(slopes of streets, cobblestones, narrow passages...) in city center
- Development of the module for the entry and presentation of the listed infrastructure
- Inserting the created traffic infrastructure into the system - Testing the upgraded version of the system Phase 3 (End - 31/12/2019) - Creating a new list of additional 1.000 accessible locations and public areas (a certain number of locations will be provided by Althea and Tourism Organization of Belgrade) - Creating a list of all public transport stops in the city center - Creating a list of all available public transport lines - Development of the module for the entry and presentation of all public transport stops and available city lines - Development of the module for entering and presenting all accessible parking spaces for people with disabilities - Data entering - Interface improving (first redesign) Phase 4
(End - 31/12/2020) - Creating a new list of additional 500 accessible locations and public areas (a certain number of locations will be provided by Althea and Tourism Organization of Belgrade)
- Creating a list of the city traffic infrastructure (dropped curbs, tactile guide lines, sound traffic lights, accessibility of
underground passages) and terrain constitution(slopes of streets, cobblestones, narrow passages...) in the wider city center
- Creating a list of all public transport stops in the wider city center - Creating a list of all available public transport lines in the wider city center
- Basic system functionality improvement Phase 5
(end - 31/12/2021)
- Creating a new list of additional 1.000 accessible locations and public areas (a certain number of locations will be provided by Althea and Tourism Organization of Belgrade) - Virtualization of 100 most visited locations
- Interface improving (second redesign)